Governor Kelly Announces KDOT awarded $62.6M for 18th Street Bridge Replacement Project In Kansas City

TOPEKA – Governor Laura Kelly announced today the U.S. Department of Transportation (U.S. DOT) has awarded the Kansas Department of Transportation (KDOT) a $62.6 million Bridge Investment Program grant for the 18th Street Bridge Replacement Project in Kansas City, Kansas.

“The health of our transportation infrastructure is vital to the safety of all who travel on Kansas’ roads, bridges, and highways,” Governor Laura Kelly said. “The 18th Street bridge has been a critical connection for decades, and this project will support continued success and growth in the area.”

The 18th Street bridge over the Kansas River in Wyandotte County is part of U.S. 69 and a key link for Kansas City neighborhoods. Built in 1959, the bridge has had many repairs over the years, but now it’s beyond restoration and needs to be replaced.

Upon inspection in 2017, the bridge was immediately closed for corrosion and cracking repairs. During this closure, from April to December 2018, comprehensive repairs were made, extending the bridge’s life. However, a long-term plan was needed as the bridge was nearing the end of its service life, and maintenance was no longer cost-effective.

“Bridges are absolutely vital to our public infrastructure – not just as part of our state highway system, but as crossings within communities,” Secretary of Transportation Calvin Reed said. “KDOT appreciates the emphasis the U.S. DOT has placed on updating our existing bridges, such as the one on 18th Street over the Kansas River.”

In 2019, KDOT completed a study to evaluate bridge options and identify a preferred alternative. During this study, the 18th Street Bridge Replacement Project Team developed a range of alternatives, which were compared and evaluated using various engineering factors. This study’s key goals were maintaining the Kansas River crossing and improving safety for travelers through the U.S. 69 (18th Street) corridor.

The bridge currently has four 12-foot lanes with narrow shoulders measuring two to three feet wide; the new bridge will use modern design standards with 10-foot exterior shoulders and 6-foot interior shoulders. It will also include visually appealing designs for the fencing over the railroad and the exterior concrete pattern, which will be consistent with the pattern used on the Lewis and Clark Viaduct, which connects Kansas City, Kansas, to Kansas City, Missouri.

“We are extremely grateful for the grant award. We pledge to work diligently with our federal and state partners to make this bridge project successful, and we are committed to strengthening our partnerships to address other critical bridge needs within our community,” said Tyrone Garner, Unified Government Mayor. “Bridge infrastructure represents the lifeblood of transportation arterial connections that make a city and community work, thrive, and grow.”

KDOT will implement additional improvements in the corridor to utilize the full closure of 18th Street while the bridge is being replaced. These improvements will include roadway improvements along 18th Street just north and south of the Kansas River and bridge rehabilitation on the 18th Street bridges over Ruby Avenue, Metropolitan Avenue, Kansas City Terminal Railway, and Osage Avenue.

Construction is scheduled to begin in 2025, and the 18th Street Bridge will be closed to traffic throughout the duration of construction. This full closure is estimated to last approximately 24 months.

U.S. DOT Bridge Investment Program grants focus on funding for existing bridges to reduce the overall number of bridges in poor condition or in fair condition at risk of falling into poor condition. The program also expands opportunities for all levels of government to apply for and be direct recipients of program funds to advance projects that meet local community needs.  

More information on the 18th Street Bridge Replacement Project can be found here: https://18thstreetbridgekck.ksdot.gov/.

For additional details on the U.S. DOT Bridge Investment Program, visit https://www.fhwa.dot.gov/bridge/bip/.

Hot this week

Flood Watch Issued Across Portions of Kansas, Nebraska, Iowa, and Missouri as Multiple Rounds of Heavy Rain Approach

The National Weather Service has issued Flood Watches for parts of Kansas, Nebraska, Iowa, and Missouri from Tuesday evening to late Thursday due to a moisture-laden system bringing 2 to 4 inches of rain, with some areas receiving up to 5 inches. Residents in flood-prone areas are urged to stay alert and follow safety precautions.

Big Blue River Enters Flood Stage Following Heavy Rains as Tuttle Creek Lake Levels Rise

Heavy rainfall in northeast Kansas and southeast Nebraska has caused the Big Blue River to flood, expected to crest at 36 feet soon. Tuttle Creek Lake is also rising, with inflow increasing significantly. The U.S. Army Corps of Engineers reduced outflow to manage rise. Residents are advised to follow safety guidelines amid flooding risks.

🎙️ Hanover High School’s “The Wildcat Wire” – 09/30/2026

Tune into the Hanover High School's "The Wildcat Wire"...

Sunday Is The Last Chance To See Seven State Historic Sites This Season

The Kansas Historical Society encourages visitors to take advantage...

Latest Headlines

KNDY Area High School Football Scores – 10/2/2026

In recent high school football games, Abilene edged Clay Center in overtime, 17-14. Other notable results include Council Grove's 46-41 victory over Marysville and Axtell's commanding 62-14 win against Troy. Centralia defeated Valley Heights 47-7, while Riley County shut out Minneapolis 42-0. Several teams had open dates.

🎙️ Coaches Corner: Marysville Bulldogs – 10/02/2026

Coaches Corner: Marysville Bulldogs - 10/02/2026

🎙️ Coaches Corner: Washington County Tigers – 10/02/2026

Coaches Corner: Washington County Tigers - 10/02/2026

KDOT Announces Approved September Bids

The Kansas Department of Transportation has approved bids for various state highway projects during a letting on September 16 in Topeka. The projects span multiple districts, including asphalt resurfacing, sealing, and bridge replacements, with significant contracts awarded to local firms. Total funding amounts reach into the hundreds of millions.

Big Blue River Enters Flood Stage Following Heavy Rains as Tuttle Creek Lake Levels Rise

Heavy rainfall in northeast Kansas and southeast Nebraska has caused the Big Blue River to flood, expected to crest at 36 feet soon. Tuttle Creek Lake is also rising, with inflow increasing significantly. The U.S. Army Corps of Engineers reduced outflow to manage rise. Residents are advised to follow safety guidelines amid flooding risks.

🎙️ Coaches Corner: Valley Heights Mustangs – 10/01/2026

Coaches Corner: Valley Heights Mustangs - 10/01/2026
- Advertisement -

Related Articles

Popular Categories

- Advertisement -